Reports to programme coordinator

All consortium members are requested to submit the financial reports of their organization to the programme coordinator every six months. This will facilitate the work of the coordinator, who should timely report to the EC. Any issues, content-wise, that should be taken into account in the progress reports to the EC should be reported to the programme coordinator as soon as the issue arises. The table below lists the dates at which consortium partners should report to the programme coordinator (30 days after the end of each reporting period).

# Period Due date
1 October 2012-March 2013 30 April 2013
2 April 2013-September 2013 30 October 2013
3 October 2013-March 2014 30 April 2014
4 April 2014-September 2014 30 October 2014
5 October 2014-March 2015 30 April 2015
6 April 2015-September 2015 30 October 2015
7 October 2015-March 2016 30 April 2016